description: Over one long weekend, Cybertrol Engineering upgraded a large animal feed facility that was comprised of multiple legacy PLC's and HMI platforms.
---

[Case Studies | Control System Integration | Success Stories ](https://blog.cybertrol.com/case-studies)

# [PLC Upgrade with Minimal Downtime for a Large Feed Plant | Cybertrol](https://blog.cybertrol.com/case-studies/case-study/large-feed-plant-plantwide-plc-upgrade)

 Written by [Cybertrol Engineering](https://blog.cybertrol.com/case-studies/author/cybertrol-engineering) | Mar 31, 2020

*A major feed processor needed to upgrade a large facility with minimal downtime.*

#### Challenge

The producer had several PLCs and HMIs on obsolete hardware. The system was comprised of approximately 20 racks of I/O and three different PLCs. The hardware had to be upgraded using minimal downtime. The upgrade included replacing HMIs on different platforms.

#### Solution

The upgrade included:

- PLC-5 to ControlLogix conversion kits (7 racks)
- SLC to CompactLogix conversion (1 rack)
- RSView32 to FactoryTalk View SE conversion
- PanelView 700 to PanelView Plus 6 700 conversion
- Remote rack RIO network to EtherNet/IP conversion
- VFDs RIO to EtherNet/IP conversion
- Mettler-Toledo scales RIO to EtherNet/IP conversion

#### Results

After the controls hardware was upgraded over a long weekend, the operators saw no discernible difference, other than the HMI experiencing faster performance.

[View full post](https://blog.cybertrol.com/case-studies/case-study/large-feed-plant-plantwide-plc-upgrade)

```json
{
  "@context" : "http://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Cybertrol Engineering"
  },
  "dateModified" : "2026-04-17T20:28:29.265Z",
  "datePublished" : "2020-03-31T05:00:00Z",
  "headline" : "A Plantwide PLC Upgrade with Minimal Downtime for a Large Feed Plant",
  "image" : {
    "@type" : "ImageObject",
    "height" : 500,
    "url" : "https://content.cybertrol.com/hubfs/Imported_Blog_Media/LargeFeed.jpg",
    "width" : 900
  },
  "mainEntityOfPage" : "https://blog.cybertrol.com/case-studies/case-study/large-feed-plant-plantwide-plc-upgrade",
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "height" : 60,
      "url" : "/hs/hsstatic/content_shared_assets/static-1.4092/img/default-amp-logo.png",
      "width" : 60
    },
    "name" : "Case Studies"
  }
}
```